The company completed the first quarter of 2017 evaluation of the project departments of Fuqing

发布日期:2019-12-12

In order to further standardize the comprehensive management of the group of professional contracted projects by the group company, in accordance with the nuclear safety regulations "Quality Assurance Safety Regulations for Nuclear Power Plants" HAF003-1991, the QHSE management system and the "Manner of the Werner Nuclear Holding Group Co., Ltd." Shenhe Holding Group Co., Ltd. Safety Management Compilation Procedures and relevant requirements of its procedural documents, the Engineering Management Department of the Group Corporation organized and co-operated with the Safety and Environment Department, Quality Assurance Department, Technology Department, and Personnel Department on March 29-31, 2017. The company's self-contracted projects such as the Fuqing lifting, special vehicle projects, industrial equipment management projects, and operation support projects have been evaluated and inspected in the first quarter of 2017. The assessment team was led by the company's deputy general manager Wang Zhaorui, the deputy manager of the project management department Tian Haiming as the deputy team leader, and other relevant department personnel.

1493004550198396.png

Site inspection guidance

The inspection and assessment work is divided into four stages: the mobilization meeting before the inspection and assessment, the inspection of the on-site data and documents, the normative inspection of the actual work on site, and the communication meeting for the summary report.

1493004555952856.png

Inspection site 1

1493004559969664.png

Inspection site 2

Through this company's internal self-inspection and self-inspection, not only the problems existing in the daily management of each project were found in time, and valuable experience was summarized; at the same time, the safety awareness was strengthened, and the safety management level of the project personnel was effectively improved; At the same time, the production capacity of the company's project departments and the ability to organize and coordinate management will be improved, which will lay a solid foundation for the project departments to continue to better serve nuclear power owners and focus on safe production.

1493004556756079.png

Inspection site 3

A total of 7 Corrective Action Requests (CAR) and 11 Observation Opinions (OBN) were issued during this inspection; (see the Attachment to the Inspection Report of the Quality Assurance Department). The relevant project department has been urged to complete the rectification and apply for verification and closure within the prescribed time.