The overhaul is approaching meticulous preparations, and the "catfish" is going all out to fight against Taiwan

发布日期:2019-12-12

Fuqing Nuclear Power's 201 overhaul is about to begin on October 1, and all units are actively preparing for overhaul.


Our project department is also doing its best to prepare for the overhaul of Fuqing Nuclear Power Plant 201.


On September 19, 2016, our project department in the classroom on the 4th floor of the Fuqing Nuclear Power Training Building held a safety mobilization meeting for all new employees who participated in the 201 overhaul.


At the mobilization meeting, all the employees who entered the factory carefully studied and signed the Safety Notice for Temporary Workers Entering Fuqing Nuclear Power.


Manager Xie Bo explained the meaning and precautions of the management procedures of our project department one by one; safety officer Zhao Shugong explained the "Fuqing Nuclear Power Industry Safety Basic Specifications" one by one; the lifting supervisor Chen Shaolin introduced the previous deviations and defects related to lifting operations, and reminded everyone to pay attention Ning Guogang gave guidance on tools borrowing, registration, and accounting. Finally, Manager Xie Bo made a concluding speech and reviewed the project department's past punishment of personnel involved in violation of regulations and discipline, and the project department was commended Happening.


On the morning of September 27, 2016, in the 8AF113 office, the project department held a tool library 201 overhaul of safety technology conference.


At the briefing, manager Xie Bo made detailed deployment of tool placement, work arrangement and shift requirements during the overhaul of tool library personnel; He Zhengyong carefully explained the characteristics, performance, and acceptance considerations of several typical tools; The procedures for borrowing and returning the tools, and the precautions were explained patiently. Finally, the representative of the owner Qin Lili, Sun Jianguo, and Shao Yiwu, the head of the service section, gave directions on the work of the tool library during the overhaul.


1487039528177247.png

A corner of the conference venue

1487039542250057.png

Representatives of owners participating in safety technology mobilization meeting

In this overhaul, our project department not only made preparations for safety knowledge and business knowledge, but also actively cooperated with brother units to make preparations for overhaul. The project department worked closely with lifting maintenance, Chengdu Haiguang, Yaomeng Electric, Shenzhen Kelly, Shanghai Shenyi, Maintenance 1 and Maintenance 2 with high-density work arrangements, and completed lifting equipment for overhaul. Counterweight test, lifting of false top cover, lifting of PX pump room sluice plate, pump motor, conventional island pad, scaffolding.

1487039876214728.png

Lifting test weight lifting 

1487039884189038.png

Nuclear island fake roof lifting

The project department originally planned to hold a lifting operation and special garage safety technology mobilization meeting in the afternoon of September 27, 2016. Unexpectedly, the meeting was postponed on September 28 due to the disruption of the typhoon "鲇鱼". Fuqing Nuclear Power started a level IV early warning and defense operation at 11:55 and a level III early warning and defense operation at 13:30.


1487040053270411.png

1487040065105660.png


At the same time, our project department was also involved in the Fuqing nuclear power station's risk elimination work. The wind was raging and the rain was heavy. In the project part, three groups set up the lifeline of the defense station in the factory area. Shaky in the wind and rain, it is difficult to stand firmly; tension in the heavy rain, the whole body is soaked.


Typhoon Catfish landed on the coast of Hui'an, Quanzhou at 4.40 in the morning on the 28th, with a wind force of 12 in the center. The night shift staff of the Anti-Taiwan Support and Driving Group of the Project Department held on for one night. Manager Xie Bo and Chen Shaolin's squad leader personally took command.