    In 2013, in order to actively respond to the prevention and control of air pollution, under the deployment of the Provincial Party Committee and Provincial Government, Zhejiang Province launched the implementation of a clean energy strategy, accelerated the pace of energy structure adjustment, increased the development and utilization of clean energy such as natural gas, and achieved significant development in clean energy. Effect.


Development of clean energy in 2013


(I) The use of clean energy continues to increase


In 2013, the province ’s clean energy utilization (including the transfer of hydropower from other provinces) into contracts was 28.57 million tons of standard coal, an increase of 7.6% year-on-year, and it is expected to account for 15.1% of the province's total energy consumption. Of which: natural gas utilization was 5.55 billion cubic meters, a year-on-year increase of 17.6%; wind power utilization was 1 billion kWh, a year-on-year increase of 28.2%; solar power generation increased significantly, utilization reached 290 million kWh, a year-on-year increase of 314.3%; biogas and other utilization Discounted coal is 1.55 million tons, a year-on-year increase of 3.3%. Received 20 billion kilowatt-hours of hydropower outside the zone, a year-on-year increase of 23.3%. As a result of unit maintenance, nuclear power generation decreased, with a utilization of 23.8 billion kWh, a year-on-year decrease of 2.2%; due to the reduction in incoming water, the province's hydropower generation reached 16.5 billion kWh, a year-on-year decrease of 8.3%.


    (II) Steady increase in clean power installations and further optimization of power structure


By the end of 2013, the province had installed 24.12 million kilowatts of clean energy, accounting for 37.0% of the province's total installed power, an increase of 2.6 percentage points and 2.58 million kilowatts over the previous year. The newly-added natural gas cogeneration unit was 2.05 million kilowatts, which accounted for 76.5% of the province's newly-added production units. A number of major clean energy projects under construction, including Fangjiashan Nuclear Power, Phase I of Sanmen Nuclear Power, and Xianju Pumped Storage, have been completed and put into operation.


    (3) The construction of natural gas storage and transportation facilities has been steadily advanced, and the storage and transportation capacity has been further enhanced.


Add 760 kilometers of natural gas provincial pipeline network and urban pipeline network. As of the end of 2013, the province has built a total of 834 kilometers of long-distance natural gas pipelines and 17955 kilometers of urban pipelines, an increase of 38.8% and 3.0% over the previous year. Provincial cities have more than 10 days of natural gas emergency reserve capacity. Fully promote the construction of the Yongtaiwen natural gas pipeline project and start the construction of the Jinliwen natural gas pipeline project in full scale. The Xiaoshan liaison station of the Shaoxing-Jiajia supporting pipeline project of the West Second Line has been completed for ventilation; the Changshan and Yiwu natural gas branch lines of the South Grid have been basically completed and have ventilation conditions. Significant breakthroughs were made in the preliminary work. The second phase of the Ningbo LNG receiving station was approved by the state. The pilot project of the LNG bunkering station of Zhoushan International Shipping and the LNG receiving station project of Wenzhou won the "Road" of the National Energy Administration; Xinjiang The coal-to-gas external pipeline project was awarded the "Road" of the National Development and Reform Commission.


(4) Renewable energy development and utilization enters the “fast track”


As of the end of December 2013, the total installed capacity of renewable energy power generation projects in the province was 8.55 million kilowatts, a year-on-year increase of 6.6% and 530,000 kilowatts, accounting for 13.1% of the province's total installed power capacity. The amount of renewable energy development and utilization (excluding foreign hydropower) was equivalent to about 8.25 million tons of standard coal, accounting for about 4.4% of the province's total energy consumption. Take a number of measures to promote the development of renewable energy: First, arrange special funds for renewable energy development of 200 million yuan. The second is to promote the construction of photovoltaic power generation projects in the province. Demonstration projects in the province have been completed with an installed capacity of 450,000 kilowatts, and the overall advancement rate of Golden Sun and other projects ranks among the top two nationwide. The third is to actively seek national policy support to promote the development of photovoltaic in our province. After active efforts, the three projects in Hangzhou, Tonglu, Shaoxing Binhai, and Hangzhou Bay, Ningbo, won the first batch of distributed photovoltaic power generation demonstration projects in China, with a total capacity of 129,000 kilowatts. The fourth is to actively promote the development of offshore wind power. The preliminary work of 6 offshore wind power projects including Guodian Zhoushan Putuo 6 and Guodian Ningbo Xiangshan 1 # has been accelerated, with an installed capacity of 1.4 million kilowatts. Its China Electric Putuo 6 wind farm has been approved in December 2013 as the first in our province. The offshore wind power project has demonstration significance. The fifth is to do everything possible to promote the grid connection of renewable energy. Actively coordinate the Zhejiang Power Grid Company to take multiple measures to promote the grid connection of renewable energy. In 2013, photovoltaic solar power was newly connected to 168,000 kilowatts, a year-on-year increase of 14 times. The sixth is to carry out technological research and development and project demonstration of solar thermal utilization, marine tidal energy utilization, and shallow geothermal energy utilization, and have achieved many innovative results.


(5) New progress in clean energy policies and regulations. The first is to further speed up the legislative work of the Regulations on the Construction and Operation Protection of Petroleum and Natural Gas Pipelines in Zhejiang Province. Two leadership group meetings were organized and the regulations were solicited and the provincial government reported to the provincial people's congress, which was included in the 2014 first-class legislative plan. The second is to implement the Regulations on Promoting the Development and Utilization of Renewable Energy in Zhejiang Province. Carry out the law enforcement inspection of the National Renewable Energy Law, and investigate the implementation of the Renewable Energy Development and Utilization Promotion Regulations of Zhejiang Province. The third is to issue and complete the "Zhejiang Natural Gas Pipeline Network Special Plan", "Natural Gas Utilization Plan" and "Research on Natural Gas Utilization Modes", "Guidelines for Petroleum and Natural Gas Safety Assessment Bureau", and "Feasibility Study on Regulations for the Protection of Petroleum and Natural Gas Pipelines in Zhejiang Province 》 And so on.


Second, 2014 work ideas


(I) Fully implement the special action plan for clean energy and increase the development and utilization of clean energy


Fully implement the Zhejiang Province Air Pollution Prevention and Control Action Plan (2013-2017) (Zhezheng Fa [2013] No. 59), vigorously implement the special action plan for clean energy in Zhejiang Province, and increase the development and utilization of clean energy. Vigorously promote the use of natural gas, continue to use nuclear power efficiently under the premise of ensuring safety, accelerate the development of renewable energy such as wind power, solar photovoltaic, and improve the level of utilization of external hydropower. Aim for the province's clean energy utilization in 2013 to reach 37 million tons of standard coal, an increase of about 29% over 2012. Among them: the utilization of natural gas reached 8 billion cubic meters, an increase of about 44% over 2013; the utilization of non-fossil energy reached about 27 million tons of standard coal, an increase of about 24% over 2013.


(2) Accelerating the construction of key clean energy projects


Further promote the construction of projects such as Sanmen Nuclear Power, Qinshan Fangjiashan Nuclear Power, Xianju Pumped Storage, and a number of natural gas rush construction projects. Ensure the production of one nuclear power unit, and strive to build more than 500,000 kilowatts of solar photovoltaic power and 150,000 kilowatts of wind power throughout the year. Three national distributed photovoltaic power generation demonstration projects including Ningbo Hangzhou Bay were completed, and the construction experience of Jiaxing Xiuzhou District photovoltaic power generation demonstration projects was actively summarized and gradually promoted. Accelerate the early stage and construction of offshore wind power projects, strive to start construction of Guodian Putuo No. 6 offshore wind farm as soon as possible, and strive to approve another 1-2 offshore wind power projects. Continue to accelerate the development and utilization of renewable energy such as biomass energy, ocean energy and geothermal energy. Promoting the approval of Zhoushan LNG receiving station and Wenzhou LNG receiving station projects; advancing the construction of the second phase of Ningbo LNG receiving station and the construction of Yantaiwen natural gas pipeline and Jinliwen natural gas pipeline; cooperating with the approval of Xinjiang coal-to-gas external pipeline Fight for work.


(3) Strengthening the legislation and implementation of clean energy


Continue to speed up the legislative work of the "Regulations on the Construction and Operation Protection of Petroleum and Natural Gas Pipelines in Zhejiang Province," and strive for early review and approval. Continue to implement the "Regulations on Promoting the Development and Utilization of Renewable Energy in Zhejiang Province". We will increase public opinion and safety inspections on the protection of oil and gas pipelines in the province, and resolutely put an end to oil and gas pipeline accidents.