The first loading of Hainan Nuclear Power Unit 1 was successfully completed

发布日期:2019-12-16

The first loading of Hainan Nuclear Power Unit 1 was successfully completed


Source: China National Nuclear Corporation Date: 2015-08-31

     

15083101.jpg

     

At 10:43 on August 28th, as the 121st group of nuclear fuel assemblies were successfully loaded into the reactor, it marked the successful completion of the first loading of Hainan Nuclear Power Unit 1.


The first loading of Unit 1 started at 14:33 on August 26, and took 44 hours.


For this loading work, Hainan Nuclear Power Co., Ltd. is well organized and relaxed. The realization of this milestone node has laid a solid foundation for Unit 1's subsequent first critical, grid-connected, and formal commercial transportation. (He Xin)