The eighth major revision of Unit 1 of Qinshan Third Nuclear Power Plant begins

发布日期:2019-12-16

At 02:53 on March 31, Unit 1 of Qinshan Third Nuclear Power Plant was disconnected from the East China Power Grid, and the eighth refueling overhaul officially started.


This overhaul is the first 10-year overhaul of domestic heavy water reactor units. The planned maintenance period is 64 days and the planned grid connection time is June 2, 2015.