Overhaul Prelude

发布日期:2019-12-13

The upcoming 303 overhaul in October is the last of the four overhauls of the No. 2 plant today. As a non-standard annual overhaul, the 303 overhaul strives to exceed the planned construction period of 30 days and achieve the first of the four units of the No. 2 plant within 30 days. Goals of the annual overhaul. As the two main maintenance units of this overhaul, since September, everyone has been carrying out the preparatory work in an orderly manner. Although we are in auxiliary positions, we also have personal experience in our daily work.


The preparation of the overhaul work package officially began at the end of August. After returning from the maintenance support office, the various teams claimed the project in charge, that is, they began to prepare documents to review the copied drawings and procedures. This involves the issue of file management and control. As a file administrator, you must update the file version in time to ensure that all drawings and procedures are the latest version. The preliminary work is also preparing for the overhaul. It happens that the latest drawing regulations come back into effect. The first thing that comes to work in the past few days is to quickly replace the new version of the document for easy reference. In case of missing drawings or problems, it is necessary to contact relevant personnel to make up in time. Sometimes, if there is a problem with a drawing, it is necessary to confirm it back and forth. Although the matter is small, the difference is so small that it is thousands of miles away. We dare not neglect at all, try our best to avoid human error, and eliminate the hidden dangers of security when it is not yet in its infancy. In addition to drawings and procedures, technical transformation documents have also recently increased a lot. The generation of documents is often controlled at various levels, and then modified after modification. And the number of daily work tickets has skyrocketed, and office filing cabinets are full. Because the integrated department of the interface and the maintenance support are located in the production building inside UD1, and we work outside of UD1, sometimes we have to go back and forth several times a day to submit technical modification documents and work tickets, or under the hot sun or rain. Can't stop us at all.


303 overhaul, short construction period, less personnel and heavy tasks, the preparatory work is very important to successfully complete the overhaul task. Nothing is too big, the rules and drawings are updated in a timely manner, self-examination and overhaul work packages, field equipment inspections, and verification of the availability of special tools ... everyone in each post is busy and dedicated to doing their job. It laid a solid foundation for the smooth progress of the 303 overhaul.


But this is only the overture of the overhaul, the real test is still waiting for the overture of the overhaul. With a positive work attitude, full of enthusiasm for work, 303 overhaul, we are waiting for it.