On October 18, 2018, the 203 overhaul progressed into the 18th day in an orderly manner. Two gates of Unit A (2CFI001BU and 2CFI003BU) of Unit 2 were lifted from the main line on the workstation. As the main body of this project, Wanna Lifting Project Department has Be prepared and ready to go.


At around 2:30 pm, the work ticket was retrieved, and the operation team staff was in place. As the maintenance support department, the work was focused on the work. The relevant staff of the service department had already been waiting at the 2PX outdoor work site earlier.


To meet the lifting conditions of the sluice, the balance valve needs to be opened to discharge water, and the liquid level difference between the two sides of the sluice should be adjusted within 0.8 meters. The overhaul period must be counted against every second. It is most time-saving to lift the standard 0.8-meter liquid difference node, and the shift is on duty for 4 hours. The liquid level is always paid attention to. The lifting conditions meet the requirements, and the gate lifting work begins.



At 7:30 in the late autumn, the night is already thick, with cool breeze, stars and raindrops, revealing the coolness, coupled with the small space in the PX outdoor area and the complicated environment, increasing the risk of this lifting work. All operators tightened the safety string and supervised each other. The on-site supervisors paid close attention to each risk point of the lifting process and reminded them at all times to ensure that the entire lifting process was carried out safely and orderly.


The secret to the successful completion of this task lies in the high sense of responsibility of each member of the staff, and always adhere to the safety barriers of each post, the road barriers interweave a solid safety net to protect the safe operation.


Responsibility is in mind and responsibility is in line. Wanna lifting team will, as always, meet the high standards of the maintenance support department to meet every challenge.


1540803266870824.jpg

1540803267362906.jpg



                                                                                                  The material receiving work of Unit 4 was completed safely and smoothly

The nuclear fuel reception of Unit 4 of Fuqing Nuclear Power started with May 7th and ended on the morning of May 11th with the joint efforts of the receiving members. It took one week's work day to complete the safe and smooth reception of all fuel assemblies.


In order to complete the receiving work safely and smoothly, the Maintenance Support Department attached great importance to it. Chief Shao Yiwu exchanged views with the receiving staff many times. Senior engineer Guo Hui reviewed the training materials personally.


1526459159598251.jpg

                                                                                                                                                  Scene picture 1


The Wannashen nuclear fuel operation team also went all out. The project manager personally conducted safety technical briefings. Each step, every action, every detail of the attention from the 0m to 20m floor was demonstrated with PPT; 0m The boss position of the cargo truck, the position of the commander, the position of the seat belt, the running track of the hook, and the use of the traction rope are all clearly explained; the 14-meter unpacking room, the unpacking steps, the division of labor, materials Box storage, spreader storage, auxiliary lifting and car switching between unpacking are all clear and clear; 20-meter floor fuel assembly gripper operation, observation of electronic scales, tool anti-fall measures, foreign object prevention and control, man-bridge crane operation, Everything is said.


1526459161111212.png

                                                                                                                                                            Scene picture 2


Full preparation only lays a solid foundation for the safe and smooth completion of the receiving work. The key step also depends on the careful operation of the field operators. The traction rope is tightly grasped, the swing control of the bin on the diagonal line of the lifting port, and the vertical control of the auxiliary lifting when the fuel assembly is turned at 90 degrees, each step is full of operator's care and patience.


Full preparation, meticulous operation, and fine management have created a perfect result: the material receiving work of Unit 4 was completed safely and smoothly as planned!