There are four routes, and the crane operates all-weather service

发布日期:2019-12-16

The overhaul of 301 is not over yet. The minor repairs of Unit 2 are underway at the same time. The overhaul preparations of Unit 1 are also being carried out in an orderly manner. In addition, Unit 4 is rushed to escorting and driving, and the staff is busy working for a while. Almost!


In the early morning of January 4, 2018, the horizon of the East just got a little bright, and the dim yellow street lights were still blinking tiredly. The Yu Pao squadron was on its way to the Fuqing nuclear power plant and was going to participate in the morning shift of Unit 4 to transfer to the guarantor and drive. At 22:00 in the evening, Unit 4 was successfully connected to the grid, and the rush-to-guarantee operation was only completed.


Colleagues participating in the shutdown of Unit 2 were busy at this time. Into the bolt drawing machine, hanging the false top cover, the pressure vessel is really big, ... from dusk to dawn, from dawn to late night, the four shifts are connected, and the shifts can't drop the chain.


 1515549882472994.png

Guo Yanliang's team of 2PX workshop cooperated with CNNC's maintenance and replacement of the pumps. From the temporary maintenance site of the 1PX circulating pump to the 2PX circulating pump pit, the red warning line is particularly eye-catching. The circulating pump to be repaired is removed from the pump pit, and the replacement pump is heading for the upcoming job. At the top and bottom, the replacement of the circulating pump was completed smoothly and safely with the special attention of the owner.

1515549882464959.png

In preparation for the overhaul of Unit 103, it is of course necessary to participate in lifting operations. Cui Jinming's team assisted Kelly employees from 1MX0 meters to +8.5 meters and down to -7.5 meters. The scaffold pipes were hoisted one by one, and the pre-103 overhaul horn had been sounded.


The 301 overhaul movement is nearing completion. The Han Dewei team lifted the 20-meter platform from the gantry to overhaul the tools and materials stored, and the tool cabinets wrapped in red plastic cloth fell shyly onto the flatbed. Gantry crane happily sang De Shengge, as if preparing a perfect rest for the 301 overhaul.


New year and new weather, the lifting operation is always ready to perform due diligence for the lifting and lifting work of Fuqing Nuclear Power, to serve you around the clock!